D3. SCOPE OF WORK
D3.1 The funds available for this contract are $ 890,000.00.
D3.2 The major components of the Work are as follows:
(a) Demolition of existing surfacing, catch basins, manholes, light standards, and the removal of plant material as per drawings and specifications.
(b) Excavation and grading as per drawings and specifications.
(c) Supply and installation of site servicing and municipal connections, including service connections to a future bottle filling station as per drawings and specifications.
(d) Supply and installation of raised concrete planter walls and curbs per drawings and specifications.
(e) Supply and installation of Powder-coated Steel Wall and Park Sign per drawings and specifications.
(f) Supply and installation of site furnishings per drawings and specifications.
(g) Supply and installation of concrete stage c/w wood decking and Screw piles per drawings and specifications.
(h) Supply and installation of concrete surfacing per drawings and specifications.
(i) Supply and installation of planting beds as per drawings and specifications.
(j) Supply and installation of plant material as per planting schedule, drawings and specifications.
(k) Supply and installation of electrical cabinet, light Poles, Luminaires, and in-ground lights as per drawings and specifications.
D3.3 The following shall apply to the Services:
(a) Universal Design Policy http://clkapps.winnipeg.ca/DMIS/DocExt/ViewDoc.asp?DocumentTypeId=2&DocId=3604