The scope of work associated with this RFQ includes but is not limited to the supply of all materials, labour, and installation associated with Stage 1 Enabling Works – Landscaping which includes tree protection, topsoil/sod installation, tree removal and replacement, tree relocation, gravel installation, and asphalt and concrete repairs. This scope also includes a warranty period for all tree planting and transplanting, and maintenance to all materials/products as installed by the contractor. The following are additional details of the scope of work, subject to change:
- Tree protection: Approximately 540m length of tree protection fence. Tree protection must be 1.2m in height and constructed of rigid or framed materials as per City of Ottawa Tree Protection Specifications.
- Topsoil/Sod Installation: Approximately 1,850 m². Minimum 150mm topsoil. Sod planted to be level with existing curbs/pathways where applicable.
- Gravel Installation: Approximately 500 m².
- Pedestrian Concrete Paving: Approximately 20 m². 140 mm thick concrete on compacted Granular 'A' base. Expansion joints at 4.5 m, control joints at 1.5 m. Light to medium broom finish perpendicular to travel.
- Tree Removal: Approximately seven trees of varying sizes removed.
- Tree relocation: Approximately three trees of varying sizes transplanted.
- Tree replacement: Approximately three trees planted.