“It is anticipated that construction will commence October 9, 2018 (weather dependent), pending permits and approvals with conditional inspections and deficiencies completed by November 23, 2018.
This contract is a calendar day contract and shall account for typical and seasonal weather delays. In the event of an Owner delay, the Contractor shall update the scheduled immediately to reflect any changes to the completion date and submit for approval of a time extension. Delays in receiving approvals will result in a time extension only, additional costs due to delays will not be entertained.
It will be the contractor’s responsibility to schedule his forces accordingly to ensure that works are completed on schedule. Construction may be done simultaneously on multiple parts of the contract. However, the contractor shall ensure that their subcontractors are scheduled accordingly to complete the restoration of all streets without undue delay after underground servicing is complete.
PLEASE NOTE: The Municipality reserves the right to reject any or all tender submissions in whole or in part without incurring any liability whatsoever.
All amendments to the associated notice, including amended documents, plans and specifications (where applicable), are issued by the originator of the notice. MERX asks you to contact the buying agency directly for these amendments. MERX stipulates that potential bidders may also be required to register with the buying authority as a bidder/plan taker. The contact information can be found within the main tender document and/or on this notice abstract.