Site work and new construction of a day care center within an educational facility.
START: DECEMBER 2, 2019
OCCUPANCY: AUGUST 7, 2020
SITE WORK COMPLETE: AUGUST 7, 2020
TOTAL COMPLETION: AUGUST 14, 2020
Sub-Trades within these Divisions are invited to participate in this project:
Division 02 Existing Conditions
Selective Demolition
Division 03 Concrete
Concrete Formwork
Concrete Reinforcing
Cast-In-Place Concrete
Concrete Floor Cures and Finishes
Division 04 Masonry
Unit Masonry
Division 05 Metals
Structural Steel
Steel Joists
Metal Deck
Miscellaneous Metals
Division 06 Wood, Plastics, and Composites
Rough Carpentry
Finish Carpentry and Millwork
Division 07 Thermal and Moisture Protection
Building Insulation
Self-Adhered Air and Vapour Barrier Membrane
Built-Up Membrane Roofing
Sheet Metal Flashing
Fire Stopping and Smoke Seals
Caulking and Sealants
Division 08 Openings
Hollow Metal Doors and Frames
Aluminum Windows
Finishing Hardware and Schedule
Glass and Glazing
Division 09 Finishes
Gypsum Board
Porcelain and Ceramic Tile
Acoustical Ceilings
Resilient Flooring and Accessories
Painting
Division 10 Specialties
Chalkboards, Whiteboards and Tackboards
Washroom Accessories
Manufactured Specialties
Division 23 Mechanical
Division 26 Electrical
Division 32 Exterior Improvements
Synthetic Grass Surfacing
Chain Link Fence
Planting
Please contact Antonio Biancofiore @ 416-233-3663 ext. 224 or email: a.biancofiore@spectreconstruction.com
Thank you.