Notice of Intended Procurement
NAME OF PROCURING ENTITY:
The Governing Council of the University of Toronto (the “University”)
University of Toronto Mississauga
3359 Mississauga Road
Mississauga, Ontario L5L 1C6
CONTACT PERSON AND CONTRACT PERSON COORDINATES:
Danielle Hendricks – Procurement Officer, procurement.utm@utoronto.ca
PROCUREMENT DOCUMENTS:
The procurement documents are available at www.merx.com.
Note that obtaining access to the procurement documents will require prospective suppliers to register and pay a registration fee. Pricing and Payment Terms are available on the MERX website.
DESCRIPTION OF PROCUREMENT:
The purpose of this RFP is to solicit responses from vendors for the Supply and Delivery of Furniture for W G Davis Building Student Halls DV1103,1104 &1105
ADDRESS AND FINAL DATE FOR SUBMISSIONS:
Submissions must be submitted electronically at:
https://utoronto.bonfirehub.ca/opportunities/88533
On or before February 14, 2025 @ 2:00:00 PM local time.
The submissions will not be opened publicly.
We strongly recommend that you give yourself sufficient time and at least ONE (1) day before Closing Time to begin the uploading process and to finalize your submission.
CONDITIONS FOR PARTICIPATION:
The RFP Process is open to all parties submitting a Proposal in accordance with the RFP Documents.
EVALUATION CRITERIA
Experience and qualifications - 10 Points
Quality and conformance with specifications – 40 Points
Schedule – 15 Points
Warranty – 5 Points
Pricing - 30 Points
Total – 100 Points
APPLICABLE TRADE AGREEMENTS:
This procurement is subject to the following trade agreement(s):
The Canadian Free Trade Agreement, Chapter Five
The Ontario-Quebec Trade and Cooperation Agreement, Chapter 9
CONTRACT DETAILS:
Project Milestones
1. Award of the furniture contract – End of February 2025
2. All furniture items should be ready to be delivered to Project site on 30 April 2025.
3. Installation and set in place to be completed by 9 May 2025
NOTES:
Suppliers should note that information contained within this notice is subject to change. Suppliers are encouraged to obtain the procurement documents which contain the most current information. If there is a conflict between the procurement documents and this notice, the procurement documents will take precedence.