SCOPE OF WORK
The Work shall consist in the supply of all supervision, labour, plant, tools, equipment, materials (including but not limited to topsoil/seed and sod), transportation, and warranty of workmanship and materials supplied by the Contractor, as required to supply and complete general landscaping and boulevard landscaping repairs to meet City of Brandon Standard Construction Specifications all in accordance with this Request for Quotation. The City of Brandon Standard Construction Specification can be found at http://brandon.ca/standard-construction-specifications. The work shall be performed within a 160km radius of the City of Brandon.
CONTRACT DURATION/WORK SCHEDULE
The Purchaser expects the work to commence on or about July 1, 2017 for a period of one (1) year to June 30, 2018 and will be on an as required basis. The Purchaser reserves the right to extend the contract for up to two (2) additional one (1) year periods.
The Purchaser will typically provide the Contractor with two weeks prior notice to schedule work unless otherwise mutually agreed. In carrying out the Work, the Contractor shall have reasonable latitude to organize the sequence of the Work, provided that the various stages of the Work are completed by the specified date(s) or the date(s) proposed by the Contractor and accepted by the Purchaser.
Final restorations shall commence within two weeks after the utility work has been completed, weather permitting, as requested by the Purchaser. Quicker commencement time may be required depending upon the location of the restorations required.