SECTION I – PTH 1 W/B (Bituminous Pavement)
Construction of bituminous pavement, including pulverizing the existing bituminous pavement, on the westbound lanes of Provincial Trunk Highway 1, from the junction of Provincial Trunk Highway 11 to the junction of Provincial Road 308, for a total construction distance of approximately 21.7km, in the Municipality of Reynolds,
SECTION II – PTH 1 E/B (Bituminous Pavement)
Construction of a bituminous pavement overlay, including milling of existing bituminous pavement and reconstruction of pavement cross-fall, on the eastbound lanes of Provincial Trunk Highway 1, from the junction of Provincial Trunk Highway 11 to the Greater Winnipeg Water District (GWWD) Railway, for a total construction distance of approximately 5.4km, in the Municipality of Reynolds,
SECTION III – PTH 1 E/B and W/B (Intersection Improvements at Falcon West Estates)
Intersection improvements, including construction of a left turn lane on the eastbound lanes and a right turn lane on the westbound lanes of Provincial Trunk Highway 11, for a total construction distance of approximately 0.4 km, in the Municipality of Reynolds,
SECTION IV - PTH 1 E/B and W/B (Spot Road Improvements)
Mill and pave the existing bituminous pavement on both the eastbound and westbound lanes of Provincial Trunk Highway 1, approximately 4.5km west of the Brokenhead River, for a total construction distance of approximately 0.2km, in the Municipality of Reynolds.